Which action is required before you renumber a Cisco UCS chassis?

← → navigate · a answer
Community votes
C
100% (2)
A
0% (0)
B
0% (0)
D
0% (0)
Discussion · 6
5
C is right Decommissioning is done when a chassis is physically present and connected, but you want to temporarily remove it from the Cisco UCS Manager configuration. Since a decommissioned chassis is expected to be recommissioned later, Cisco UCS Manager keeps part of the chassis' information for future use
2
https://www.cisco.com/c/en/us/td/docs/unified_computing/ucs/sw/cli/config/guide/3-0/b_UCSM_CLI_User_Guide_3_0/b_UCSM_CLI_User_Guide_3_0_chapter_0100011.pdf
2
If you are swapping IDs between chassis, you first have to decommission both chassis, then wait for the chassis decommission FSM to finish before moving on with the renumbering steps.
1
The correct answer is C = Decommission the chassis Managing the Chassis - Cisco.pdf
C 1
Selected Answer: C C is right as Cobach says
1
C is right!