ETExamTower
Q50Storage Network

Refer to the exhibit. An engineer is configuring an FCoE connection between a Cisco UCS and a Cisco Nexus 9000 Series Switch. UCS FI-A connects to the Nexus switch through interface e1/12. All relevant configurations on the Nexus switch to support the FCoE deployment have been completed. Which action must be performed in Cisco UCS Manager to finish the configuration?

Question exhibit
← → navigate · a answer
Community votes
D
100% (3)
A
0% (0)
B
0% (0)
C
0% (0)
Discussion · 2
D 5
Selected Answer: D D is the correct answer. vFC is created on the N9K side, not the UCS side https://www.cisco.com/c/en/us/support/docs/servers-unified-computing/ucs-manager/116188-configure-fcoe-00.html
D 2
Selected Answer: D as per the linked doc, it's D