Q56Network Access
Refer to the exhibit. PC1 regularly sends 1800 Mbps of traffic to the server. A network engineer must configure the EtherChannel so that Port Channel 1 between SW1 and SW2 is disabled when the Ge0/0 and Ge0/1 interfaces on SW2 go down. Which configuration must the engineer apply to the switch?
← → navigate · a answer
Community votes
Discussion · 10
2
Option C
Option C: lacp max-bundle 2 sets the maximum number of links that can be bundled into port channel 1. This option effectively disables the port channel when only one or no links are available, which aligns with the desired behavior of disabling the channel when both Ge0/0 and Ge0/1 are down
A 2
Selected Answer: A
A. SW2# configure terminal -
SW2(config)# interface port-channel 1
SW2(config-if)# port-channel min-links 2
This command configures the minimum number of links that have to be up in the port-channel for it to remain active as 2. If both ports go down, the EtherChannel will be disabled, which is the intended result in the scenario shown. Please note that the port-channel number should match the actual port-channel being configured, which is 1 according to the exhibit, not 4 as shown in the answer choices. This is probably a typo in the provided answer options.
2
This is not CCNP question, it is dumb question. They ask us to change the config of port channel 1 but use port channel 4 for all the answers lol. Cisco doesnt even know how their own devices work!
1
A
The port-channel min-links command says the minimum number of interfaces that the configuration mode LAG needs to be active
1
According to this documentation, the answer is A.
https://www.cisco.com/c/en/us/td/docs/switches/lan/catalyst9200/software/release/17-2/configuration_guide/lyr2/b_172_lyr2_9200_cg/configuring_etherchannels.html#id_97595
A 1
Selected Answer: A
A is correct.
A 1
Selected Answer: A
A is correct
1
please revised my answer, it should be C,
1
This is not a CCNA question. This is a CCNP question.
1
don't confuse max and min